| 2011/08 |
WFC Lens arrived at the summit. |
Hawaii |
| |
New Prime Focus Unit (PFU) arrived at the summit. |
Hawaii |
| 2011/09 |
Docking of WFC mechanical mock-up and PFU |
Hawaii |
| |
FEU shipping |
Tokyo |
| 2011/10 |
New PFU + mock WFC telescope mount rehearsal |
Hawaii |
| 2011/11 |
116 CCDs installation into the cryostat |
Tokyo |
| |
HSC Camera System Testing |
Tokyo |
| 2012/03 |
HSC Camera System shipping |
Tokyo |
| 2012/06 |
Docking of WFC and PFU |
Hawaii |
| 2012/08 |
Engineering First Light |
Hawaii |
| 2013/01 |
2nd test observing |
Hawaii |
| 2013/06 |
3rd test observing |
Hawaii |
| 2013/10 |
4th test observing |
Hawaii |
| 2014/01 |
5th test observing |
Hawaii |
| 2014/03 |
Start of scientific observations |
Hawaii |