Schedule



2011/08 WFC Lens arrived at the summit. Hawaii
  New Prime Focus Unit (PFU) arrived at the summit. Hawaii
2011/09 Docking of WFC mechanical mock-up and PFU Hawaii
  FEU shipping Tokyo
2011/10 New PFU + mock WFC telescope mount rehearsal Hawaii
2011/11 116 CCDs installation into the cryostat Tokyo
  HSC Camera System Testing Tokyo
2012/03 HSC Camera System shipping Tokyo
2012/06 Docking of WFC and PFU Hawaii
2012/08 Engineering First Light Hawaii
2013/01 2nd test observing Hawaii
2013/06 3rd test observing Hawaii
2013/10 4th test observing Hawaii
2014/01 5th test observing Hawaii
2014/03 Start of scientific observations Hawaii